The Department of Transport advises that Hydromaster will undertake a geophysical survey campaign in relation to the Clogherhead Offshore Wind Farm off the coast of Co Louth.

The survey is expected to run from Monday 11 September to Saturday 18 November, subject to operational and weather constraints.

Works will be conducted by the Ros Áine (callsign EIZG5) using multi-beam echo sounders, sub-bottom profilers, side-scan sonars, magnetometers and ultra-high-resolution survey equipment.

Geophysical equipment will be both hull-mounted and towed. Typically, the towed cable lengths will be approximately four times the water depth that the vessel is working in while acquiring survey data.

The work will be conducted during daylight hours only. Throughout operations, the vessel will display the appropriate lights and shapes and will also be restricted in its ability to manoeuvre. Therefore, passing vessels are requested to leave a wide berth.

Radio transmissions will be conducted with other seafarers to notify them of ongoing operations. Mariners are advised to keep continuous watch on VHF radio channel 16 when navigating the area. The survey vessel shall monitor this channel continuously for safety purposes.

Coordinates and a map of the survey area as well as contact details can be found in Marine Notice No 57 of 2023, attached below.

Published in Power From the Sea

Techworks Marine is deploying three surface buoys with single-point moorings for a metocean survey campaign at the site of the proposed Clogherhead Offshore Wind Farm.

It follows a geophysical survey campaign conducted by Alpha Marine this past summer, as previously reported on Afloat.ie.

These deployments are expected to be completed over a two-day period, at the next available weather window from Sunday 6 November, subject to weather and operational constraints.

Once deployed, the met ocean devices will remain on site for a period of up to 12 months.

The survey campaign will be undertaken within the proposed Clogherhead Offshore Wind Farm site, located some 10km from the Co Louth coast. Detailed coordinates and a map of the survey area are included in Marine Notice No 76 of 2022, attached below.

Three yellow buoys will be deployed, each with a hull diameter of 1.2m and a nominal freeboard of 0.7m. The buoys will display a St Andrew’s Cross day mark, and are fitted with a radar reflector and navigation light with a three nautical mile range, flashing a sequence of five flashes every 20 seconds.

Deployment operations will be conducted by the twin-hulled multi-cat work vessel MPV Skua (callsign 2GDE3).

During works, the vessel will be restricted in its ability to manoeuvre so all other vessels are requested to leave a wide berth during the deployment operations. Radio transmissions will be conducted with other seafarers to notify them of the operations.

Published in Power From the Sea

Alpha Marine will undertake a geophysical survey campaign in relation to the Clogherhead Offshore Wind Farm off the coast of Co Louth from next Thursday 25 May to Wednesday 27 July.

The survey will be conducted by the Baltic Explorer (callsign LYBW) utilising multibeam echo sounders, sub-bottom profilers, side-scan sonars, magnetometers and ultra-high-resolution survey equipment.

Geophysical equipment will be both hull-mounted and towed. Typically, the towed cable lengths will be about four times the water depth while acquiring survey data.

The work will be conducted on a 24-hour basis and the work vessel will display appropriate lights and signals. Mariners are advised to keep continuous watch on VHF Channel 16 when navigating the area.

All other vessels operating within this area are requested to keep their distance and pass at minimum speed to reduce vessel wash.

Mariners are also asked to note that the start date and the duration of the activity are dependent on weather and work progress.

Coordinates of the survey area and contact details can be found in Marine Notice No 26 of 2022, attached below.

Published in Power From the Sea

Galway Port & Harbour

Galway Bay is a large bay on the west coast of Ireland, between County Galway in the province of Connacht to the north and the Burren in County Clare in the province of Munster to the south. Galway city and port is located on the northeast side of the bay. The bay is about 50 kilometres (31 miles) long and from 10 kilometres (6.2 miles) to 30 kilometres (19 miles) in breadth.

The Aran Islands are to the west across the entrance and there are numerous small islands within the bay.

Galway Port FAQs

Galway was founded in the 13th century by the de Burgo family, and became an important seaport with sailing ships bearing wine imports and exports of fish, hides and wool.

Not as old as previously thought. Galway bay was once a series of lagoons, known as Loch Lurgan, plied by people in log canoes. Ancient tree stumps exposed by storms in 2010 have been dated back about 7,500 years.

It is about 660,000 tonnes as it is a tidal port.

Capt Brian Sheridan, who succeeded his late father, Capt Frank Sheridan

The dock gates open approximately two hours before high water and close at high water subject to ship movements on each tide.

The typical ship sizes are in the region of 4,000 to 6,000 tonnes

Turbines for about 14 wind projects have been imported in recent years, but the tonnage of these cargoes is light. A European industry report calculates that each turbine generates €10 million in locally generated revenue during construction and logistics/transport.

Yes, Iceland has selected Galway as European landing location for international telecommunications cables. Farice, a company wholly owned by the Icelandic Government, currently owns and operates two submarine cables linking Iceland to Northern Europe.

It is "very much a live project", Harbourmaster Capt Sheridan says, and the Port of Galway board is "awaiting the outcome of a Bord Pleanála determination", he says.

90% of the scrap steel is exported to Spain with the balance being shipped to Portugal. Since the pandemic, scrap steel is shipped to the Liverpool where it is either transhipped to larger ships bound for China.

It might look like silage, but in fact, its bales domestic and municipal waste, exported to Denmark where the waste is incinerated, and the heat is used in district heating of homes and schools. It is called RDF or Refuse Derived Fuel and has been exported out of Galway since 2013.

The new ferry is arriving at Galway Bay onboard the cargo ship SVENJA. The vessel is currently on passage to Belem, Brazil before making her way across the Atlantic to Galway.

Two Volvo round world races have selected Galway for the prestigious yacht race route. Some 10,000 people welcomed the boats in during its first stopover in 2009, when a festival was marked by stunning weather. It was also selected for the race finish in 2012. The Volvo has changed its name and is now known as the "Ocean Race". Capt Sheridan says that once port expansion and the re-urbanisation of the docklands is complete, the port will welcome the "ocean race, Clipper race, Tall Ships race, Small Ships Regatta and maybe the America's Cup right into the city centre...".

The pandemic was the reason why Seafest did not go ahead in Cork in 2020. Galway will welcome Seafest back after it calls to Waterford and Limerick, thus having been to all the Port cities.

© Afloat 2020