Menu

Ireland's sailing, boating & maritime magazine

Displaying items by tag: Ferguson Marine

The considerably delayed newbuilds for Scotland ferry operator, Caledonian MacBrayne (CalMac) which are being built at Ferguson Marine shipyard, Port Glasgow, will it has emerged carry fewer passengers than first envisioned.

As STV reports, the reduction in passenger capacity of the leadship twins, Glen Sannox and recently named Glen Rosa, is in response to safety certification measures as required by the regulator, the Maritime and Coastguard Agency (MCA).

This will see each ferry with a maximum carrying capacity of 1,000 reduced to 852 passengers, a difference of 148 in the original design of the newbuilds, with the first the Glen Sannox Afloat highlights was due to enter service in 2018.

Chief executive of the Scottish Government-owned shipyard, David Tydeman said the cost of the newbuilds has risen further, see previous coverage.

In a letter sent last week to MSP’s, he said Calmac and the agency Caledonian Maritime Assets Ltd (CMAL) were considering a maximum capacity of 852 passengers to accommodate the required number of stairwells and passageways.

On Tuesday, transport minister Fiona Hyslop said CMAL would only take delivery of the newbuilds, once they had been signed off by the MCA, in addition to the regulator, the class society, which surveys ships.

The minister told the Scottish Parliament that all systems including the Liquid National Gas (LNG) propulsion system will need to be completed, something which will require special pipework.

More here on the ongoing ferry story.

Published in Shipyards

As the shipyard ferry fiasco in Scotland continues, ministers in Edinburgh have come under fire as new estimates suggest the cost of the dual-fuel powered newbuilds could reach £400m.

The figure for the CalMac ferries, does not include the millions pumped into the nationalised shipyard Ferguson Marine to keep it operating, amounts to over four times the £97m contract cost for the two lifeline ferries to serve on Arran on the Forth of Clyde.

Both newbuilds, Glen Sannox and the recently named twin, Glen Rosa following a public vote, still await delivery at the Inverclyde shipyard, downriver of Glasgow.

Chief executive of Ferguson Marine, David Tydeman indicated that it will cost an extra £240 million to build the ferries on top of what was previously spent before the nationalisation of the shipyard took place in 2019.

As The Herald, which more on the story, reports that £83.25 million was spent on the ferries prior to the Scottish Government taking control of the shipyard firm with an additional £45 million on loan.

Published in Shipyards

In Scotland the ferry bosses which own Caledonian MacBrayne (CalMac) vessels, have revealed the name of the second delayed newbuild under construction by Ferguson Marine shipyard on the Clyde.

The long-delayed ferry which for years has only been known as Hull 802, is to be named the Glen Rosa following a list of selected names given in an online public vote.

Caledonian Maritime Assets Ltd (CMAL), the body which owns CalMac vessels as well as the port and harbour infrastructure, announced the name from the listed options: Glen Coy, Glen Rosa and Claymore. 

In the public vote, nearly 5,000 people took part in the name the ferry competition.

Of the three names, Glen Rosa, which is Gleann Ruasaidh in Gaelic, was the public’s most popular, winning 52 per cent of all votes cast.

The dual-fuel powered ferries, each of 102m in length, were due to enter service in 2018 at a price of £97 million, however delays have led to spiralling costs which could amount to more than three times that figure.

More from The Scotsman on the 1,000 passenger newbuild.

The winning name Afloat adds refers to the glen near Goat Fell (874m) the highest point on Arran in the Firth of Clyde where the newbuild will also serve with twin Glen Sannox also being built at Ferguson Marine.

The ferries, each capable of carrying 127 cars or 16 HGVs, or a combination of both will operate on the Ardrossan-Brodick, Arran route.

They will operate on both liquefied natural gas (LNG) and marine diesel. LNG is significantly cleaner and has been adopted by ferry operators in northern Europe in response to tighter emissions regulations

Published in Shipyards

Twin dual-fuel powered ferries being built at Ferguson Marine shipyard on the Clyde are facing further delays after demands for design changes by the safety regulator.

According to the Maritime and Coastguard Agency (MCA) doors will have to be modified and extra staircases installed on both the M.V. Glen Sannox and the unnamed Hull 802.

Both newbuilds, with around 1,000 passengers each, are to serve CalMac's Ardrossan-Brodick (Arran) route, were to have scheduled sea trials, however they will now be delayed until the first few months of 2024.

The Glen Sannox which was launched in 2018, is due to enter service on CalMac's busiest route, by the end of 2023 while the Hull 802 is not set to take to water with passengers until summer 2024.

Managing director of the Inverclyde shipyard, David Tydeman at Holywood, told the Scottish Parliament's transport committee that he hopes to reach a final agreement with the safety regulator within the next two weeks
.
STV News has more on this latest development affecting the timeframe of the newbuild's delivery into service.

Published in Shipyards

In Scotland, ministers of the Government intend to return the troubled shipyard of Ferguson Marine to the private sector, a senior Scottish National Party minister has confirmed.

The SNP minister Neil Gray and Cabinet Secretary for Wellbeing Economy, Fair Work and Energy, said it was hoped the shipyard (located downriver of Glasgow at Port Glasgow) could become commercially successful again.

Ferguson Marine as Afloat has reported over the years, has been at the centre of controversy over the construction of two newbuild ferries for CalMac, a subsidiary of David MacBrayne Ltd, which is wholly owned by Scottish Ministers.

The first of the two newbuilds of around 5,000 gross tonnage, the Glen Sannox and an unnamed twin are substantially delayed and overbudget.

Each of the 102m ferries have a capacity for 1,000 passengers, 127 cars and 16 lorries that are to serve island communities and tourism.

In March a report by Audit Scotland had raised doubts over the long-term viability of the shipyard, which was to have completed building the first of the ferries in 2018 at the yard that in the following year was nationalised.

For more, The Scotsman reports.

Published in Shipyards

Glen Sannox, the massively delayed Scottish ferry for operator CalMac, will need nearly two months of further tests before the 1,000 passenger capacity vessel can enter service on the Firth of Clyde.

In addition the duel-fuelled powered ferry which is to serve the Isle of Arran route, will also have to undergo "extensive” sea trials prior to completion by shipyard Ferguson Marine which John Swinney related to MSPs last week.

CalMac, has confirmed to The Scotsman, of the duration of the additional “familiarisation and network trials” that will be required before the hybrid newbuild will be able to operate on the Ardrossan-Brodick route.

Such trials of the 102m newbuild is likely to increase the pressure to have the new ferry ready for next year’s summer season after Deputy First Minister announced a further delivery delay at the shipyard owned by the Scottish government.

The delay at the Clydeside shipyard, is now to see the 16.5 knot ferry enter from May to this autumn, if not the end of the year.

A twin of Glen Sannox, the as-yet unnamed hull (#802) to operate between Uig, Harris and North Uist, will also be delayed, from March 2024 to “late summer”, if not the end of the year.

According to spending watchdog, Audit Scotland they expect the project to cost at least £293 million – this amount is three times the cost of the original contract and as Afloat reported the Glen Sannox was due to enter service in 2018.

More here on the shipbuilding story. 

Published in Shipyards

Shipyard chief executive David Tydeman told MSPs in a letter on Wednesday that the two ferries, which are five years late, would cost up to £209.6 million to complete compared to the previous estimate of up to £122m.

According to The Scotsman, that would mean a total cost of around £300m, including some £83m previously spent, compared to the original contract of £97m.

A damning report into the fiasco by public spending watchdogs Audit Scotland in March had estimated the final cost would be at least £240m.

Mr Tydeman said the second ferry, known as hull 802, is not now expected to be handed over until the first quarter of 2024 compared to the previously scheduled timescale of between October and December 2023.

It is being built at the Port Glasgow yard for the Skye-Harris-North Uist triangle route.

Mr Tydeman also said in the update to the Scottish Parliament’s net zero, energy and transport committee that there was a “one to two month worst case slippage in final handover” of Glen Sannox, or 801 – the first vessel (for Arran route on the Forth of Clyde). 

More here on the Clydeside shipyard. 

 

Published in Shipyards

The First Minister of Scotland, Nicola Sturgeon has said she will “not apologise” for decisions taken with the aim of saving the shipyard Ferguson Marine.

The Clyde yard was nationalised in 2019, but island communities are still awaiting the delivery of two new ferries (see CalMac naming story), with the project facing delays as well as being over-budget.

Earlier this week, businessman Jim McColl hit out at the First Minister over her claim that the yard would have closed had the Government not intervened.
McColl accused the SNP leader of lying about the number of jobs that were saved at the yard at the time and said there was “no danger” of the yard closing at the time.

The First Minister, however, has defended the actions taken by her government, as she pointed to 400 workers who are currently employed at the yard.
Scottish Conservative leader Douglas Ross raised the issue at First Minister’s Questions on Wednesday – being held a day early at the Scottish Parliament due to the local election on Thursday.

STV News has further coverage on the shipyard issue raised at Holyrood, the Scottish parliament.

Published in Shipyards

Clydeside shipyard Ferguson Marine announced on Monday, the completion of a major milestone in the build of one of the dual fuel ferries currently under construction.

Hull 802, as the vessel is currently known, was fitted with its large bow unit which is the largest single unit added to the ferry’s steel hull, completing the bow structure.

This week will mark a key moment in the vessel’s progress when the final units are lifted into place, completing the main hull and steelwork and making way for the installation of the ferry’s aluminium superstructure, which is all the units that sit above the main deck.

Over the coming weeks and months, resources will ramp up to around 150 people working on Hull 802 to support the construction effort.

The National has more on the Port Glasgow yard which Afloat adds is constructing the ferry for CalMac's Uig Triangle service.

Whereas the first ferry when completed, Glen Sannox is to serve on the Arran service on the Firth of Clyde.

Published in Shipyards

Scottish Ministers admit that further problems with lifeline ferries languishing in a Clydeside shipyard will delayed by eight months and will add a further £8.7m to the costs taking the bill to a quarter of a billion pounds.

Finance secretary Kate Forbes admitted that cabling issues has meant further delays to the ferries ever setting sail - a day after an public spending auditor's report revealed doubts that they will ever go into service.

Audit Scotland criticised a “multitude of failings” in the delivery Glen Sannox (Arran service) and Hull 802 which are languishing in the state-controlled Ferguson Marine yard were now nearly five years late and will cost the public two-and-a-half times the contract costs - £240m.

After the latest costs uplift and delay emerged, Scottish Conservatives' shadow transport secretary Graham Simpson said the SNP should be "ashamed" by the auditors analysis and called for a public inquiry.

Scottish Labour shadow transport secretary Neil Bibby challenged Ms Forbes to resign if the latest rescheduling is not stuck to.

Herald Scotland last week reported on the shipyard saga. 

Published in Shipyards
Page 1 of 3

Dun Laoghaire Harbour Information

Dun Laoghaire Harbour is the second port for Dublin and is located on the south shore of Dublin Bay. Marine uses for this 200-year-old man-made harbour have changed over its lifetime. Originally built as a port of refuge for sailing ships entering the narrow channel at Dublin Port, the harbour has had a continuous ferry link with Wales, and this was the principal activity of the harbour until the service stopped in 2015. In all this time, however, one thing has remained constant, and that is the popularity of sailing and boating from the port, making it Ireland's marine leisure capital with a harbour fleet of between 1,200 -1,600 pleasure craft based at the country's largest marina (800 berths) and its four waterfront yacht clubs.

Dun Laoghaire Harbour Bye-Laws

Download the bye-laws on this link here

FAQs

A live stream Dublin Bay webcam showing Dun Laoghaire Harbour entrance and East Pier is here

Dun Laoghaire is a Dublin suburb situated on the south side of Dublin Bay, approximately, 15km from Dublin city centre.

The east and west piers of the harbour are each of 1 kilometre (0.62 miles) long.

The harbour entrance is 232 metres (761 ft) across from East to West Pier.

  • Public Boatyard
  • Public slipway
  • Public Marina

23 clubs, 14 activity providers and eight state-related organisations operate from Dun Laoghaire Harbour that facilitates a full range of sports - Sailing, Rowing, Diving, Windsurfing, Angling, Canoeing, Swimming, Triathlon, Powerboating, Kayaking and Paddleboarding. Participants include members of the public, club members, tourists, disabled, disadvantaged, event competitors, schools, youth groups and college students.

  • Commissioners of Irish Lights
  • Dun Laoghaire Marina
  • MGM Boats & Boatyard
  • Coastguard
  • Naval Service Reserve
  • Royal National Lifeboat Institution
  • Marine Activity Centre
  • Rowing clubs
  • Yachting and Sailing Clubs
  • Sailing Schools
  • Irish Olympic Sailing Team
  • Chandlery & Boat Supply Stores

The east and west granite-built piers of Dun Laoghaire harbour are each of one kilometre (0.62 mi) long and enclose an area of 250 acres (1.0 km2) with the harbour entrance being 232 metres (761 ft) in width.

In 2018, the ownership of the great granite was transferred in its entirety to Dun Laoghaire Rathdown County Council who now operate and manage the harbour. Prior to that, the harbour was operated by The Dun Laoghaire Harbour Company, a state company, dissolved in 2018 under the Ports Act.

  • 1817 - Construction of the East Pier to a design by John Rennie began in 1817 with Earl Whitworth Lord Lieutenant of Ireland laying the first stone.
  • 1820 - Rennie had concerns a single pier would be subject to silting, and by 1820 gained support for the construction of the West pier to begin shortly afterwards. When King George IV left Ireland from the harbour in 1820, Dunleary was renamed Kingstown, a name that was to remain in use for nearly 100 years. The harbour was named the Royal Harbour of George the Fourth which seems not to have remained for so long.
  • 1824 - saw over 3,000 boats shelter in the partially completed harbour, but it also saw the beginning of operations off the North Wall which alleviated many of the issues ships were having accessing Dublin Port.
  • 1826 - Kingstown harbour gained the important mail packet service which at the time was under the stewardship of the Admiralty with a wharf completed on the East Pier in the following year. The service was transferred from Howth whose harbour had suffered from silting and the need for frequent dredging.
  • 1831 - Royal Irish Yacht Club founded
  • 1837 - saw the creation of Victoria Wharf, since renamed St. Michael's Wharf with the D&KR extended and a new terminus created convenient to the wharf.[8] The extended line had cut a chord across the old harbour with the landward pool so created later filled in.
  • 1838 - Royal St George Yacht Club founded
  • 1842 - By this time the largest man-made harbour in Western Europe had been completed with the construction of the East Pier lighthouse.
  • 1855 - The harbour was further enhanced by the completion of Traders Wharf in 1855 and Carlisle Pier in 1856. The mid-1850s also saw the completion of the West Pier lighthouse. The railway was connected to Bray in 1856
  • 1871 - National Yacht Club founded
  • 1884 - Dublin Bay Sailing Club founded
  • 1918 - The Mailboat, “The RMS Leinster” sailed out of Dún Laoghaire with 685 people on board. 22 were post office workers sorting the mail; 70 were crew and the vast majority of the passengers were soldiers returning to the battlefields of World War I. The ship was torpedoed by a German U-boat near the Kish lighthouse killing many of those onboard.
  • 1920 - Kingstown reverted to the name Dún Laoghaire in 1920 and in 1924 the harbour was officially renamed "Dun Laoghaire Harbour"
  • 1944 - a diaphone fog signal was installed at the East Pier
  • 1965 - Dun Laoghaire Motor Yacht Club founded
  • 1968 - The East Pier lighthouse station switched from vapourised paraffin to electricity, and became unmanned. The new candle-power was 226,000
  • 1977- A flying boat landed in Dun Laoghaire Harbour, one of the most unusual visitors
  • 1978 - Irish National Sailing School founded
  • 1934 - saw the Dublin and Kingstown Railway begin operations from their terminus at Westland Row to a terminus at the West Pier which began at the old harbour
  • 2001 - Dun Laoghaire Marina opens with 500 berths
  • 2015 - Ferry services cease bringing to an end a 200-year continuous link with Wales.
  • 2017- Bicentenary celebrations and time capsule laid.
  • 2018 - Dun Laoghaire Harbour Company dissolved, the harbour is transferred into the hands of Dun Laoghaire Rathdown County Council

From East pier to West Pier the waterfront clubs are:

  • National Yacht Club. Read latest NYC news here
  • Royal St. George Yacht Club. Read latest RSTGYC news here
  • Royal Irish Yacht Club. Read latest RIYC news here
  • Dun Laoghaire Motor Yacht Club. Read latest DMYC news here

 

The umbrella organisation that organises weekly racing in summer and winter on Dublin Bay for all the yacht clubs is Dublin Bay Sailing Club. It has no clubhouse of its own but operates through the clubs with two x Committee vessels and a starters hut on the West Pier. Read the latest DBSC news here.

The sailing community is a key stakeholder in Dún Laoghaire. The clubs attract many visitors from home and abroad and attract major international sailing events to the harbour.

 

Dun Laoghaire Regatta

Dun Laoghaire's biennial town regatta was started in 2005 as a joint cooperation by the town's major yacht clubs. It was an immediate success and is now in its eighth edition and has become Ireland's biggest sailing event. The combined club's regatta is held in the first week of July.

  • Attracts 500 boats and more from overseas and around the country
  • Four-day championship involving 2,500 sailors with supporting family and friends
  • Economic study carried out by the Irish Marine Federation estimated the economic value of the 2009 Regatta at €2.5 million

The dates for the 2021 edition of Ireland's biggest sailing event on Dublin Bay is: 8-11 July 2021. More details here

Dun Laoghaire-Dingle Offshore Race

The biennial Dun Laoghaire to Dingle race is a 320-miles race down the East coast of Ireland, across the south coast and into Dingle harbour in County Kerry. The latest news on the Dun Laoghaire to Dingle Race can be found by clicking on the link here. The race is organised by the National Yacht Club.

The 2021 Race will start from the National Yacht Club on Wednesday 9th, June 2021.

Round Ireland Yacht Race

This is a Wicklow Sailing Club race but in 2013 the Garden County Club made an arrangement that sees see entries berthed at the RIYC in Dun Laoghaire Harbour for scrutineering prior to the biennial 704–mile race start off Wicklow harbour. Larger boats have been unable to berth in the confines of Wicklow harbour, a factor WSC believes has restricted the growth of the Round Ireland fleet. 'It means we can now encourage larger boats that have shown an interest in competing but we have been unable to cater for in Wicklow' harbour, WSC Commodore Peter Shearer told Afloat.ie here. The race also holds a pre-ace launch party at the Royal Irish Yacht Club.

Laser Masters World Championship 2018

  • 301 boats from 25 nations

Laser Radial World Championship 2016

  • 436 competitors from 48 nations

ISAF Youth Worlds 2012

  • The Youth Olympics of Sailing run on behalf of World Sailing in 2012.
  • Two-week event attracting 61 nations, 255 boats, 450 volunteers.
  • Generated 9,000 bed nights and valued at €9 million to the local economy.

The Harbour Police are authorised by the company to police the harbour and to enforce and implement bye-laws within the harbour, and all regulations made by the company in relation to the harbour.

There are four ship/ferry berths in Dun Laoghaire:

  • No 1 berth (East Pier)
  • No 2 berth (east side of Carlisle Pier)
  • No 3 berth (west side of Carlisle Pier)
  • No 4 berth  (St, Michaels Wharf)

Berthing facilities for smaller craft exist in the town's 800-berth marina and on swinging moorings.

© Afloat 2020