The Department of Transport has been advised by Vermilion Exploration & Production Ireland Limited of a maintenance campaign that will include an offshore pipeline and subsea structure inspection at the Corrib Gas Field subsea infrastructure.

This maintenance work was due to commence on Tuesday 14 May and will last for approximately 30 days.

A nearshore survey of the pipeline and umbilical of the Corrib subsea infrastructure will also take place. These works are due to commence on Friday 17 May and will last for approximately 10 days. All work dates are subject to weather and operational constraints.

Visual and acoustic surveys will be conducted by means of vessel- and ROV-mounted sensors. Electrical fault-finding will be conducted by ROV-mounted equipment.

The vessel EDT Jane (callsign 5BXW3) will undertake the subsea scope of work as part of the offshore pipeline and subsea structure inspection. All equipment used will be vessel and/or ROV mounted.

Elsewhere, the nearshore survey scope will be undertaken by the vessel Leah C (callsign EIQS5) while the vessels Macbel” (callsign EIHL5) and the Blue Eagle (callsign EI6808) will both provide safety and welfare support to Leah C. The vessels will be listening on VHF Channel 16 throughout the project.

Further information, including a map, coordinates and contact details, can be found in Marine Notice No 23 of 2024 attached below.

Published in Coastal Notes

The Corrib gas field’s operator is pursuing a legal challenge to the Government’s windfall tax on energy.

As the Irish Independent reports, owner Vermilion Energy is arguing that it has not made any profit from the Corrib field, although revenues in 2022 were higher than previous years.

The case is before the Commercial Court.

“These significant and ongoing financial losses have not been taken into account by the State when applying the recent Temporary Solidarity Contributory Tax, as would normally be the case under prudent tax law,”Vermilion told the newspaper.

The temporary solidarity contribution on windfall gains was initiated at the European level after war broke out in Ukraine in 2022, pushing up energy prices.

Vermilion says that Ireland is an “outlier” in Europe in having set a tax rate of 75 percent, which it claims is more than double the European Council recommended minimum rate of 33 percent.

It says only Slovenia has imposed a higher rate, at 80pc

The idea of levying a tax on the sector Europe-wide has already been challenged in the courts by ExxonMobil. It lodged a case late last year with the EU General Court opposing the regulation that allowed national parliaments to impose the tax.

Read more in The Irish Independent here

Published in Power From the Sea
Tagged under

Vermilion Exploration & Production Ireland Limited is carrying out a maintenance campaign at the Corrib Gas Field subsea infrastructure, with spot rock placement along the main umbilical.

Works were due to commence in the field on Sunday 25 June to last for around three days, subject to weather and operational constraints.

The vessel FFPV Stornes (Callsign PCKX) is undertaking the subsea scope of work during day and night hours, displaying all appropriate lights and signals while carrying out rock placement activities using a fall-pipe system and associated acoustic survey equipment.

All equipment will be vessel and/or remote operated vehicle (ROV) mounted. Visual and acoustic surveys will be conducted by means of vessel- and ROV-mounted cameras and sensors. The work vessel will be listening on VHF Channel 16 throughout the project.

Coordinates and a map of the survey area as well as contact details can be found in Marine Notice No 36 of 2023, attached below.

Published in Coastal Notes

The Canadian-based operator of the Corrib gas field has increased its stake in the north Mayo project to 56.5 per cent.

Vermilion Energy says it is now “the largest provider of domestic natural gas in Ireland” after confirming acquisition of the Equinor ASA stake in the project.

The gas field’s revenues benefited from a 61 per cent increase in gas prices last year, according to the Vermilion Energy annual report for 2022.

In a statement, the Canadian energy company said the acquisition “adds an incremental 36.5% interest in the Corrib Natural Gas Project, increasing Vermilion's operated interest to 56.5%”.

The company said it had entered into an agreement with Equinor ASA in November 2021 to acquire its stake for US$434 million ($556 million), “before closing adjustments and contingent payments”.

It said net purchase price was approximately $200 million.

This net price was after “adjusting for the interim free cash flow between the effective date and closing date inclusive of Vermilion's estimates of European windfall taxes based on information released to-date on how it will be implemented in Ireland, the contingent payment and other closing adjustments”, the company said.

The acquisition “adds approximately 7,000 boe/d of premium-priced, high netback, low emission European natural gas production, further strengthening Vermilion's international portfolio”, it said.

The company described Corrib as a “world-class, low emission, natural gas facility, comprised of a conventional gas field located 83 kilometres off the northwest coast of Ireland and a state of the art gas processing plant onshore Ireland”.

“The facility has a gross plant capacity of approximately 350 million cubic feet of natural gas per day and is currently producing 115 million cubic feet of natural gas per day, representing approximately 20% of Ireland's natural gas consumption and 100% of Ireland's domestic gas production,”it said.

It said that since taking over operatorship in 2018 from Shell, Vermilion has “reduced costs and increased uptime while maintaining world-class safety and environmental performance”.

Published in Power From the Sea
Tagged under

A Mayo TD has called for windfall tax on profits of the Corrib gas field to be ring-fenced for the Erris region of north Mayo.

Sinn Féin TD Rose Conway Walsh said the company trebled profits in the first six months of 2022 to an estimated €560 million.

As the Connacht Telegraph reports, this puts it on course for €1 billion of profits for the year, she said.

The Belmullet-based TD: "The design of the windfall tax, as it is stated by the Council of the European Union, is far from perfect, as it lets the company keep the vast majority of the windfall profits.

"They keep all of their normal profits, plus an extra 20%, and then they keep 77% of the windfall profits over and above that,” she told the newspaper.

"It would be an important gesture for the people of Mayo and Belmullet, particularly for the likes of Belmullet Community Hospital and the R312,”she said.

Read more in the Connacht Telegraph here

Published in Power From the Sea
Tagged under

Vermilion Exploration & Production Ireland Limited will carry out a maintenance campaign at the Corrib Gas Field’s subsea infrastructure from next weekend.

The works are due to commence in field next Sunday 14 August and last for up to 21 days, weather allowing. Maintenance works, including pipeline and subsea structure inspection, will take place at Latitude 54° 20’ 20.413” N, Longitude 11° 03’ 30.769” W.

All works will be undertaken by the vessel EDT Jane (callsign 5BXW3). All equipment used will be vessel and/or remote operated vehicle (ROV) mounted. Visual and acoustic surveys will be conducted by means of vessel- and ROV-mounted sensors.

The vessel will be listening on VHF Channel 16 throughout the project.

Maps of the survey area and contact details are included in Marine Notice No 50 of 2022, attached below.

Published in News Update

Vermilion Exploration & Production Ireland Limited will begin a maintenance campaign at the Corrib Gas Field subsea infrastructure from tomorrow, Friday 1 October.

The maintenance works at the Corrib gas field will take place at Latitude 54° 20’ 20.413” N, Longitude 11° 03’ 30.769” W and are due to last for up to 21 days.

The Edda Sun (callsign LARF7) will undertake the subsea scope of work. All equipment used will be vessel and/or remotely operated vehicle (ROV) mounted. The vessel will be listening on VHF Channel 16 throughout the project.

Mariners are asked to note that visual surveys will be conducted along the Corrib pipelines and umbilicals using vessel mounted ROVs and their associated camera booms. No acoustic survey equipment will be utilised during the campaign.

For further information on the survey area, see Marine Notice No 51 of 2021 which can be downloaded below.

Published in News Update

Vermilion Exploration & Production Ireland Limited is scheduled to carry out maintenance work at the Corrib subsea infrastructure from next Sunday 13 June.

The maintenance work at the Corrib Gas Field will take place at Latitude 54° 20’ 20.413” N, Longitude 11° 03’ 30.769” W and is expected to take up to five days to complete.

The Edda Sun (Callsign LARF7) will undertake the subsea scope of work. All equipment used will be vessel- and/or ROV-mounted. The vessel will be listening on VHF channel 16 throughout the project.

Further information on the survey area is available Marine Notice No 36 of 2021 which can be downloaded below.

Published in Coastal Notes

Mariners in the vicinity of the Corrib Gas Field are advised of electrical fault-finding works at the field’s subsea infrastructure set for later this month.

Works conducted from the Edda Sun (callsign LARF7) will begin on or around next Friday 18 September and will last for up to 10 days. The work vessel will be listening on VHF channel 16 throughout the project.

Details of co-ordinates of the search and repair area are included in Marine Notice No 39 of 2020, which is attached below.

Published in Marine Warning

#MarineNotice - Shell E&P Ireland Limited has begun a campaign of inspection of the Corrib Gas Field pipeline and associated infrastructure with repair and maintenance as required. Engineering tasks are also scheduled for well P3.

The near shore pipeline inspection was scheduled to commence in mid July and last for approximately 10 days. The offshore pipeline and subsea structure inspection along with the P3 work is due to commence in early August 2018 and last for approximately 14 days.

Visual and acoustic surveys will be conducted by means of sensors mounted on vessels and Remote Operated Vehicles (ROV) and cameras located on attendant survey vessels, ROVs and towed side scan sonar.

The near shore pipeline and umbilical sections will be inspected from the nearest point accessible inshore at high tide progressing to offshore until a suitable overlap with the offshore inspection is achieved.

The offshore inspection will commence at the Corrib field location and will continue towards shore until the vessel is required, on Marine Mammal Observer (MMO) advice, to relocate to the inshore inspection extent at safe navigation depth limit.

The vessel An Gearoidin (Callsign EIDL6) will undertake the near shore survey scope. All the equipment used will be vessel deployed. The Macbel and Blue Eagle will provide safety and welfare support to An Gearoidin.

The Siem Stingray (Callsign LAFP8) will undertake the deep water surveys and the subsea facilities maintenance and inspection. It will also carry out the P3 rectification work. All equipment used will be vessel and/or ROV mounted. All vessels will be listening on VHF Channel 16 throughout the project.

Full details of relevant co-ordinates and a map of the survey area are included in Marine Notice No 31 of 2018, a PDF of which is available to read or download HERE.

Published in Coastal Notes
Page 1 of 5

The home club of Laser Radial Olympic Silver medalist Annalise Murphy, the National Yacht Club is a lot more besides. It is also the spiritual home of the offshore sailing body ISORA, the Dun Laoghaire to Dingle Race and the biggest Flying Fifteen fleet in Ireland. Founded on a loyal membership, the National Yacht Club at the East Pier in Dun Laoghaire on Dublin Bay enjoys a family ethos and a strong fellowship in a relaxed atmosphere of support and friendship through sailing.

Bathing in the gentle waterfront ambience of Dun Laoghaire on the edge of South County Dublin, the National Yacht Club has graced the waters of the Irish Sea and far beyond for more than a century and in 2020 celebrates its sesquicentennial.  

The club is particularly active in dinghy and keelboat one-design racing and has hosted three World Championships in recent years including the Flying Fifteen Worlds in 2003, 2019 and the SB3 Worlds in 2008. The ISAF Youth Worlds was co-hosted with our neighbouring club the Royal St. George Yacht Club in 2012...

National Yacht Club Facilities

Facilities include a slipway directly accessing Dun Laoghaire Harbour, over eighty club moorings, platform parking, pontoons, fuelling, watering and crane-lifting ensure that the NYC is excellently equipped to cater for all the needs of the contemporary sailor. Berths with diesel, water, power and overnight facilities are available to cruising yachtsmen with shopping facilities being a short walk away. The club is active throughout the year with full dining and bar facilities and winter activities include bridge, snooker, quiz nights, wine tasting and special events.

National Yacht Club History

Although there are references to an active “club” prior to 1870, history records that the present clubhouse was erected in 1870 at a cost of £4,000 to a design by William Sterling and the Kingstown Royal Harbour Boat Club was registered with Lloyds in the same year. By 1872 the name had been changed to the Kingston Harbour Boat Club and this change was registered at Lloyds.

In 1881. the premises were purchased by a Captain Peacocke and others who formed a proprietary club called the Kingstown Harbour Yacht Club again registered at Lloyds. Some six years later in 1877 the building again changed hands being bought by a Mr Charles Barrington. and between 1877 and 1901 the club was very active and operated for a while as the “Absolute Club” although this change of name was never registered.

In 1901, the lease was purchased by three trustees who registered it as the Edward Yacht Club. In 1930 at a time when the Edward Yacht Club was relatively inactive, a committee including The Earl of Granard approached the trustees with a proposition to form the National Yacht Club. The Earl of Granard had been Commodore of the North Shannon Y.C. and was a senator in the W.T.Cosgrave government. An agreement was reached, the National Yacht Club was registered at Lloyds. The club burgee was created, red cross of Saint George with blue and white quarters being sky cloud, sea and surf. The Earl of Granard became the first Commodore.

In July of 1950, a warrant was issued to the National Yacht Club by the Government under the Merchant Shipping Act authorising members to hoist a club ensign in lieu of the National Flag. The new ensign to include a representation of the harp. This privilege is unique and specific to members of the National Yacht Club. Sterling’s design for the exterior of the club was a hybrid French Chateau and eighteenth century Garden Pavilion and today as a Class A restricted building it continues to provide elegant dining and bar facilities.

An early drawing of the building shows viewing balconies on the roof and the waterfront façade. Subsequent additions of platforms and a new slip to the seaward side and most recently the construction of new changing rooms, offices and boathouse provide state of the art facilities, capable of coping with major international and world championship events. The club provides a wide range of sailing facilities, from Junior training to family cruising, dinghy sailing to offshore racing and caters for most major classes of dinghies, one design keelboats, sports boats and cruiser racers. It provides training facilities within the ISA Youth Sailing Scheme and National Power Boat Schemes.

Past Commodores

1931 – 42 Earl of Granard 1942 – 45 T.J. Hamilton 1945 – 47 P.M. Purcell 1947 – 50 J.J. O’Leary 1950 – 55 A.A. Murphy 1955 – 60 J.J. O’Leary 1960 – 64 F. Lemass 1964 – 69 J.C. McConnell 1969 – 72 P.J. Johnston 1972 – 74 L. Boyd 1974 – 76 F.C. Winkelmann 1976 – 79 P.A. Browne 1979 – 83 W.A. Maguire 1983 – 87 F.J. Cooney 1987 – 88 J.J. Byrne 1988 – 91 M.F. Muldoon 1991 – 94 B.D. Barry 1994 – 97 M.P.B. Horgan 1997 – 00 B. MacNeaney 2000 – 02 I.E. Kiernan 2002 – 05 C.N.I. Moore 2005 – 08 C.J. Murphy 2008 – 11 P.D. Ryan 2011 – P. Barrington 2011-2014 Larry Power 2014-2017 Ronan Beirne 2017 – 2019

At A Glance - National Yacht Club 2024 Events

  • 24th February Optimist Sprint
  • 25th February Leinster Schools Team Racing
  • 3rd March Leinster Schools Team Racing
  • 13th April Lift in
  • 20th April Leinster Schools Team Racing
  • 23rd – 24th, 27th – 28th April University Invitational Match Racing Championships
  • 11th – 12th May 29er Easterns and Invitational Match Racing Nationals
  • 25th – 26th May Women at the Helm Regatta
  • 15th June NYC Regatta
  • 22nd – 23rd June Topper Southern Champs
  • 10th July NYC Junior Regatta
  • 5th September NYC End of Season Race
  • 21st – 22nd September F15 East Coast Championships
  • 5th October Start of F15 Frostbite Series
  • 12th October Lift Out
  • 19th – 20th October RS Aero Easterns

Featured Sailing School

INSS sidebutton

Featured Clubs

dbsc mainbutton
Howth Yacht Club
Kinsale Yacht Club
National Yacht Club
Royal Cork Yacht Club
Royal Irish Yacht club
Royal Saint George Yacht Club

Featured Brokers

leinster sidebutton

Featured Webcams

Featured Associations

ISA sidebutton
ICRA
isora sidebutton

Featured Marinas

dlmarina sidebutton

Featured Chandleries

CHMarine Afloat logo
https://afloat.ie/resources/marine-industry-news/viking-marine

Featured Sailmakers

northsails sidebutton
uksails sidebutton
watson sidebutton

Featured Blogs

W M Nixon - Sailing on Saturday
podcast sidebutton
BSB sidebutton
wavelengths sidebutton
 

Please show your support for Afloat by donating